Shore Road Paving in Pocasset: November 2026 Schedule and Access

The town's fall notice gives this week as the window for Shore Road's new surface. The Bourne Department of Public Works said final paving was expected to start around November 2 and take 8 to 10 working days. If that schedule held, crews are working somewhere along the Pocasset stretch right now. The paving is the second of two Shore Road projects. In May the town dug up and redesigned the intersection where Barlows Landing Road meets Shore Road. The fall paving runs straight through that rebuilt corner. Together the two jobs cover most of the Shore Road route through Pocasset.

That shapes what a resident can expect between now and Thanksgiving. The work happens on weekdays only, the town says the roads stay open, and the program is scheduled to finish by November 20.

The corner came first, back in May

On Monday, May 11, DPW began work at the Barlows Landing Road and Shore Road intersection, aiming for substantial completion by Friday, June 26, according to CapeNews. The project added an all-way stop, new pedestrian curb ramps, asphalt paving, crosswalk markings and some minor drainage work.

Town Meeting had approved $423,000 for design, construction and oversight back in May 2025. Apex Companies did the engineering, and Mass Pavement Reclamation Inc. of Marshfield was the low bidder for construction. The Barlows Landing boat ramp stayed open the whole time. CapeNews reported that trailers were told to come straight into the intersection from the east on Barlows Landing Road, because the work cut into the turning room.

The corner was a small, separately funded fix. Because it was done first, the fall crews are paving through an intersection that already has its new layout and drainage.

The road came second, and it cost much more

The fall program is a bigger job. The town's Fall 2026 Paving notice puts the cost at $2,765,170, paid for with Bourne's allocation from the Massachusetts Chapter 90 Program for capital improvements on local public ways. The scope covers milling, paving and catch basin repairs on four roads: Shore Road, Red Brook Harbor Road, Squeteague Harbor Road and Megansett Road.

Barlows Landing intersection Fall 2026 paving program
Dates May 11 to about June 26 Oct. 13 to about Nov. 20
Cost $423,000 approved $2,765,170 estimated
Funding Town Meeting appropriation, May 2025 Massachusetts Chapter 90 allocation
Contractors Apex Companies for design, Mass Pavement Reclamation for construction P.J. Keating Co. and Lawrence-Lynch Corp
Scope All-way stop, curb ramps, crosswalks, drainage Milling, paving, catch basins on four roads

The fall budget is more than six times the intersection budget. The money also comes from a different place: the corner was paid for with a local appropriation, and the road surface with state Chapter 90 money. They were planned and paid for as separate projects, but on the ground they make one continuous route.

How the work moves down the road

According to the notice, P.J. Keating started milling where Shore Road meets Trowbridge Road and worked south along Shore Road, then moved on to Red Brook Harbor Road, Squeteague Harbor Road and Megansett Road. The town estimated 8 to 10 days for milling. Lawrence-Lynch Corp was scheduled to start rebuilding catch basins and other structures around October 19.

The DPW's tentative milling and paving calendar splits the job into segments of about a mile each, and the paving follows roughly the same order the milling did:

  1. Shore Road near County Road, Old Dam and the Monument Beach ball field, paved south in sections of about a mile.
  2. Shore Road starting at Barlows Landing, paved south and southwest about a mile toward the railroad bridge.
  3. The stretch from the railroad bridge toward County Road, along with Red Brook Harbor Road.
  4. Squeteague Harbor Road and Megansett Road, toward the town line.

The calendar also marks one holiday that week with no work scheduled. The town's November calendar lists offices closed for Veterans Day on November 11. The top of that calendar says it is "Subject to Change Without Notice," and the official notice puts it the same way:

All work is weather dependent, and the schedule is subject to change.

If you live on Shore Road between Barlows Landing and the railroad bridge, your section sits in the middle of the paving sequence. If you live in Cataumet, off Red Brook Harbor or Megansett, your roads come last.

What it's like to drive it this week

Work hours are 7 a.m. to 4:30 p.m., Monday through Friday. The town says roads stay open and access to homes and businesses is maintained. Signs, police officers and flaggers direct drivers and pedestrians through the work zones. Until the new surface goes down, the notice warns drivers, bicyclists and residents to expect temporary delays, uneven pavement, faded or missing markings, raised structures and more noise.

The raised structures are the catch basin and utility covers Lawrence-Lynch rebuilt in October, left sticking up above the milled road until the final paving comes up level with them. Pavement markings go back down once paving is done. The tentative calendar shows one more step after that, with Lawrence-Lynch adjusting structures on all four roads. The town expects the whole program to wrap up by November 20.

Because the work stops on weekends, the weekend drive is the easy one. A Saturday trip along Shore Road this month passes through work zones with no equipment in them.

Places along the route this month

The fall work stays on the road itself. Barlows Landing Road leads inland from the rebuilt corner, and the regular stops along it aren't part of this job.

  • Four Ponds Conservation Area–Bourne Town Forest, 140 Barlows Landing Road. The town owns it. The Buzzards Bay Coalition's listing describes four trails starting from a free gravel lot on Barlows Landing Road, with posted hours of 5 a.m. to 10 p.m. Check those hours before an early walk, since the listing has no date.
  • Graziella's, 375 Barlows Landing Road, 508-563-5541. The address and phone number come from the restaurant's contact page.
  • Barlows Landing boat ramp, at the corner rebuilt in May and June. If you're trailering a boat, the all-way stop and new crosswalks are now permanent.

Farther south on the route, the Chart Room at 1 Shipyard Lane, inside Kingman Yacht Center, already shows "Closed for the Season" on its website. It opens on weekends in spring and fall and every day from the last week of June through Labor Day. So the Cataumet end of the paving runs past a quiet waterfront this month.

Two Bourne events fall around the paving calendar, both on days the crews aren't working or after they finish. On Saturday, November 7, Anna's Pals holds "Bourne to Run," a 3.5-mile community race that starts and finishes at the former Hoxie School, 30 Williston Road, Sagamore Beach, according to CapeNews. In Buzzards Bay, Cape Cod's Polar Express returns, with First Responders Night on November 14 and approved parking at Taylor Point Marina from November 21 through December 23, as CapeNews reported.

By the time the Polar Express parking opens, the town's schedule has Shore Road finished, with fresh markings from Trowbridge Road south through the new Barlows Landing corner to the Cataumet roads at the town line. For questions about your own stretch, the Bourne DPW can be reached at 508-759-0600, the number listed in the town's construction notice.

If you're wondering what a fully rebuilt Shore Road means for a home on the Pocasset side of Bourne, Shana Lundell would be glad to walk the route with you and talk it through. Let's Connect.